August - September 201309/21/2013 Аrsky Branch After ground works recultivation of allocated part of earth side cutting is done on site “Reconstruction of the auto road Kutuk – Kazanbash in Arsky district of the Republic of Tatarstan”. 09/20/2013
Slopes are being stabilized on site “Construction of the auto road “Buraly-Rantamak”-Aleksandrovka”-Almetiyevsk-Musliumovo”-Tatarskiye Karamaly” in Sarmanovsky district of the Republic of Tatarstan. 09/20/2013 Menzelinsky Branch Asphalt bedding course is being laid on site “M-7 Volga” – Noviy Melken” in Menzelinsky district of the Republic of Tatarstan. 09/18/2013 Menzelinsky Branch Site “Reconstruction of the auto road “Verkhniy Tabyn - Togashevo” in Musliumovsky district of the Republic of Tatarstan. Here, sand-and-gravel mix bottom course is being constructed using mix-in-place method and roadbed slopes are being leveled. 09/17/2013 Sabinsky Branch Construction of the auto road “Verkhniy Iskubash – Nizhniy Iskubash” – Bitlyangur in Kukmorsky district of the Republic of Tatarstan is finished. 09/13/2013 Menzelinsky Branch Site “Reconstruction of the auto road “Verkhniy Tabyn - Togashevo” in Musliumovsky district of the Republic of Tatarstan. Here, sand-and-gravel mix is being delivered and prepared for construction of bottom course using mix-in-place method. 09/13/2013 Mamadyshsky Branch The construction of pavements, protective works on conduit pipes and mounting of guard rails are being finished on site “Reconstruction of the auto road “Ishkeyevo – Nizhniy Takanysh” – Chaksy. 09/13/2013 Mamadyshsky Branch Construction of the road bed and asphalt course is finished on site “Reconstruction of the auto road “Kemesh-Kul – Algayevo” in Mamadyshsky district of the Republic of Tatarstan. 09/13/2013 Аrsky Branch Construction of sand-and-gravel mix bottom course and macadam road bed is finished on site “Reconstruction of the auto road Kazan-Shemordan, km 63+504 – km 65+434 in Tulyachinsky district of the Republic of Tatarstan. Asphalt bedding course is being laid. 09/11/2013 Menzelinsky Branch Site “M-7 Volga” – Noviy Melken” in Menzelinsky district of the Republic of Tatarstan. Here, bottom course is being constructed using mix-in-place method, stabilized with sand-and-gravel mix and cement. 09/10/2013 Аrsky Branch Asphalt-concrete is being laid on site “Reconstruction of the auto road Pechmentau-Stariy Kiner in Arsky district of the Republic of Tatarstan. 09/04/2013 Menzelinsky Branch Asphalt-concrete surface course is being laid on site “Construction of the auto road “Almetiyevsk- Musliumovo” – Igenche” in Musliumovsky district of the Republic of Tatarstan. 09/03/2013 Menzelinsky Branch Ground course is being stabilized with lime on site “Reconstruction of the auto road “Verkhniy Tabyn - Togashevo” in Musliumovsky district of the Republic of Tatarstan. 09/01/2013 Аrsky Branch Roadsides are being stabilized with M-400 macadam on site “Reconstruction of the auto road Pimeri – Yunusovo in Pestrechinsky district of the Republic of Tatarstan”. 08/29/2013 Suburban Branch Racking course of porous fine-graded bituminous concrete is being laid on site “Reconstruction of the auto road “Kazan-Orenburg” – Rybnaya Sloboda – Kornoukhovo” – Bolshoy Oshnyak – Malyi Oshnyak in Rybno-Slobodsky district of the Republic of Tatarstan”. 08/28/2013
Sandy subsoil with geogrid above is being laid on site “Construction of the auto road “M-7 “Volga” – Kutlu -Bukash – Rybnaya Sloboda – Bikchurayevo in Rybno-Slobodsky district of the Republic of Tatarstan”. 08/28/2013
Reinforced concrete pipe is being mounted on site “Construction of the auto road “Buraly-Rantamak” – Aleksandrovka” – Almetiyevsk – Musliumovo” – Tatarskiye Karamaly” in Sarmanovsky district of the Republic of Tatarstan”. 08/28/2013 Sabinsky Branch Reconstruction of the auto road “Kazan – Shemordan”, km 90+400 – km 98+607 in Sabinsky district of the Republic of Tatarstan. Single-coat asphalt course 6 cm thick of dense asphalt-concrete mix type Б and М-2 was laid on part “Drive to school” 0.640 km long. 08/28/2013 Sabinsky Branch Construction of the auto road “Kukmor – Shemordan”-Nyriya-Ishtugan”- Baldy Knya in Kukmorsky district of the Republic of Tatarstan. Base course 0.18 m thick 0.995 km long of M-800 macadam is being made here. 08/28/2013 Suburban Branch Subsoil with geogrid above and base course are being laid on site “Construction of the auto road “Peschyaniye Kovali – Orlovka” – Tarlashi in Laishevsky district of the Republic of Tatarstan”. 08/24/2013 Mamadyshsky Branch Sowing and land recultivation of easement areas on site “Construction of the auto road “Ishkeyevo – Nizhniy Takanysh – Chaksy ”, km 1+500 – km 6+200 in Mamadyshsky district of the Republic of Tatarstan”. 08/24/2013
Earth excavations are being made on site “Reconstruction of the auto road “Ulanovo – Karatun” – Kaby Kopri, part Utiyamishevo – Kaby Kopri in Apastovsky district of the Republic of Tatarstan”. 08/24/2013 Apastovsky Branch Reconstruction of the auto road “Kazan – Uliyanovsk” – Staroye Baryshevo – Kamskoye Ustiye” – Yasashno- Baryshevo in Apastovsky district of the Republic of Tatarstan is finished. 08/24/2013 Apastovsky Branch Reconstruction of the auto road “Normalization of the road net in settlement Maliye Bolgoyary” in Apastovsky district of the Republic of Tatarstan is finished. 08/23/2013 Apastovsky Branch Construction of the auto road “Drive to village Labyshka” in Kamsko-Ustiynsky district of the Republic of Tatarstan is finished. 08/23/2013 Apastovsky Branch Reconstruction of the auto road “Kazan-Uliyanovsk” – Staroye Baryshevo – Kamskoye Ustiye” Almenderovo - Maliye Bolgoyary”, km 0+000 – km 4+230 in Apastovsky district of the Republic of Tatarstan is finished. 08/22/2013 Menzelinsky Branch ЩМА – 15 macadam and mastics wearing course was laid on site “M-7 “Volga” – Stariy Irkenyash – Tatarskaya Mushuga” in Menzelinsky district of the Republic of Tatarstan”. 08/22/2013 Mamadyshsky Branch Macadam road bed and base and wearing courses are being constructed on the auto road “Usali-Albay-Vladimirovo”. 08/21/2013 Suburban Branch Base course of porous coarse grain asphalt concrete is being constructed on site “Construction of the auto road Obukhovo-Tagashevo in Laishevsky and Pestrechinsky districts of the Republic of Tatarstan”. 08/21/2013 Menzelinsky Branch Construction of asphalt concrete base course is almost finished on site “Tiukovo – Tatarskiye Yamaly”, km 17+550 – km 21+000 in Aktanyshsky district of the Republic of Tatarstan”. 08/21/2013 Menzelinsky Branch Topsoil stripping and constructional works are being made on site “Verkhniy Tabyn – Togashevo” in Musliumovsky district of the Republic of Tatarstan”. 08/21/2013 Menzelinsky Branch Road subsoil and concrete pipe foundation are being constructed on site “Almetiyevsk – Musliumovo” – Igenche” in Musliumovsky district of the Republic of Tatarstan”. 08/21/2013 Mamadyshsky Branch Double-coat asphalt concrete coating was laid on the bridge across Shumbutka river on km 917 of auto road M-7 “Volga”. 08/21/2013 Mamadyshsky Branch Earth roadbed is being constructed on site “Reconstruction of the auto road Kemesh-Kul – Algayevo in Mamadyshsky district of the Republic of Tatarstan”. 08/21/2013 Nizhnekamsky Branch Reconstruction of auto roads in Nizhnekamsk. 08/14/2013 Аrsky Branch On site “Reconstruction of the auto road “Kazan-Shemordan-Yambulat km 0+00 – km 2+00 in Tulyachinsky district of the Republic of Tatarstan” the lower road structure is being constructed using “mix-in-place” cold regeneration method with addition of cement and bitumen emulsion to the enriched sand and gravel mix. 08/05/2013 Аrsky Branch On site “Reconstruction of the auto road “Arsk-Tulyachi” – Bolshoy Shinar in Sabinsky district of the Republic of Tatarstan” the ground works are being finished, the lower road structure is being constructed on km 0+00 – km 13+70, and asphalt bedding course is being laid. 08/02/2013 Menzelinsky Branch Reconstruction of the auto road “M-7 Volga – Novy Melken”in Menzelinsky district of the Republic of Tatarstan. Here, water pipe conduit is being constructed. 08/02/2013 Menzelinsky Branch On site “Reconstruction of the auto road “Tiukovo – Tatarskiye Yamaly” km 17+550 – km 21+000 in Aktanyshsky district of the Republic of Tatarstan” the lower road structure is being constructed using “mix-in-place” method of stabilization with sand and gravel mix and cement. |